Thursday 8 November 2007

Works On Site

The Chairman, Barrie McDowell, has been working closely with St James on some of the outstanding jobs on site. We are pleased to report that:

Crossover and steps between Sherbooke Way and Beaumont Drive have been completed. The tarmac’d areas will receive a resin-bonded finish in the spring (this type of surface needs to be installed in warmer weather).

The speed bumps on Beaumont Drive will be fitted next week (WB 12 November) – Dennis is going to have a look and decide where the best locations are to install these to minimise inconvenience to residents.

EDF (the company responsible for power on site) has now completed a survey of the amphitheatre and confirmed the installation process for the phased power supply and we are now awaiting confirmation of an installation date.

Finally, the bike store plans for Phase 1 have had to be amended as a site survey showed that the doors would not have fitted correctly. An amended detail is currently being produced and it is currently anticipated that the works will start during week commencing the 19th November.